Al Zour Liquefied Natural Gas (LNG) Termainal, Kuwait

WJ have been an established part of the dewatering industry in the Middle East for other 15 years now since providing dewatering for the Dubai International Airport Terminal 3 development back in 2003, and have long established offices in Dubai and Qatar. This project marked our expansion in the region to neighbouring Kuwait and the Al Zour Liquefied Natural Gas (LNG) Terminal project, a development that, when finished, will be the largest LNG refinery in the Middle East!

The new terminal is located in the Al-Zour region of Kuwait near to the border with Saudi Arabia, approximately 90km south of the capital Kuwait City, and will include eight LNG storage tanks, each with a capacity of 225,000m3, and associated marine facilities.

Although the sandy ground conditions were prime dewatering territory, the project had the potential to be particularly challenging. Not only would WJ be working in a new country which always brings with it a steep learning curve, but the structures to be dewatered were far from insubstantial – the intake and outfall structures which our systems were going to target were approximately 500m by 200m in size, and up to 15m deep, and the works would be taking place on land reclaimed from the Arabian Gulf. Fortunately there are few things WJ love more than a challenge!

In order to complete the works in a swift and prompt fashion WJ utilised one of our trusted partners, Trevito work alongside our own SM14 drilling rig. In total 62 dewatering wells and 10 groundwater monitoring standpipes were installed for the intake structure, and another 21 for the outfall structure. The initial plans were to install both perimeter and internal dewatering systems to draw the groundwater level down to enable a dry excavation, however the perimeter system proved to be so successful that there was no need for the internal system to be installed.

Although the works began at the start of 2018 when the temperatures in Kuwait are relatively comfortable, as the project has progressed the day time working temperatures approached the 40°Cs and as the Muslim holy month of Ramadan arrived it became necessary for some of the installation works to be undertaken during the night, with only monitoring to be undertaken during daylight hours. This however had no impact upon the expert level of service WJ are known for.

  • LOCATION: Al Zour, Kuwait
  • MAIN CONTRACTOR: Hyundai

Features

  • Deepwell Systems
  • Excavations
Share

Related Projects

Fairlight Cove Coastal Protection

Fairlight Cove Coastal Protection

  • Siphon System
  • -Read More-
  • Big Data Institute, Oxford

    Big Data Institute, Oxford

  • Deepwell Dewatering
  • -Read More-
  • Salford Dallas Court Detention Tank

    Salford Dallas Court Detention Tank

  • Remediation
  • Deepwell Dewatering
  • -Read More-